Which of the following methods involves performing tasks in parallel?

Which of the following methods involves performing tasks in parallel?

Which of the following is an example of a project?
a. Maintaining e-mail addresses
b. Capacity planning
c. Submitting travel and expense reports
d. Sending monthly reports to top management

Which of the following methods involves performing tasks in parallel?2. An effective project manager must:
a. Tell his team members what to do
b. Be the most capable person on the team technically
c. Be focused on achieving results
d. Not trust his team members to achieve results without his personal attention to detail

3. A key characteristic of an effective project team is that:
a. Members have graduate degrees in project management
b. Members come from the same professional background
c. Members see themselves as stakeholders in the project
d. Members adhere to a prescribed pecking order

4. A challenge of the matrix project organization is that:
a. Team members are full of ego
b. Team members are selected from the same functional area
c. Team members have divided loyalties
d. It enables functional managers to provide career guidance to their workers

5. A key weakness of the Benefit-Cost ratio project selection mechanism is that:
a. It only focuses on things that can be measured
b. It takes time frame into consideration
c. It is too much based on subjective judgment
d. It does not entail prioritizing

6. A major strength of task Gantt charts is that they can:
a. Offer a sophisticated model of a project
b. Show how many resources will be used on the project
c. Show the interdependencies of tasks
d. Show actual versus planned schedule status

7. If you want to shorten the length of a project, you must:
a. Shorten the critical path
b. Shorten the free float
c. Spend more money

d. Cut back on the features you plan to deliver

8. The critical path:
a. Provides the duration of a project
b. Has the shortest duration on a project
c. Is the most expensive path to implement
d. Contains the project’s most significant tasks

9. A tool that graphically shows cost variance is:
a. A chart of accounts
b. A code of accounts
c. A histogram (also called a resource loading chart)
d. A cumulative cost curve (also called S-curve)

10. Which of the following methods involves performing tasks in parallel?
a. Crashing
b. Fast tracking
c. Leveling
d. Hammocking

11. Top-down estimates (also called parametric estimates):
a. Are based on historical trends
b. Can be derived from the WBS
c. Can be determined by analyzing work packages
d. Provide accurate assessments of project costs

12. Bottom-up estimates:
a. Are based on historical trends
b. Can be derived from the WBS
c. Must employ Monte Carlo simulation
d. a and c

13. Definitive estimates are generally derived from:
a. Bottom-up estimates
b. Top-down estimates
c. Expert judgment cost estimates
d. Order of magnitude estimates

14. The resource planning tool that enables us to identify who we need to carry out what tasks is called:

a. A resource Gantt chart
b. A resource matrix (also called the responsibility chart)
c. A resource ogive
d. A resource loading chart (also called a resource histogram)

15. Which of the following shows resource allocation over time?
a. Resource Gantt chart
b. Resource matrix
c. S-Curve
d. Resource leveling

16. What is the function of a change control board (CCB) in configuration management?
a. To assess the management impacts of change requests
b. To initiate changes needed on the project
c. To focus on the technical implication of change requests
d. To approve change requests coming from senior management

17. Good functional requirements
a. Describe how the deliverable should be developed
b. Provide detailed technical insights into what the deliverable will do
c. Describe what the deliverable looks like and what it should do
d. Are created after development of the technical specifications

18. The type of management whose focus is on activities whose variances lie outside the acceptable range is:
a. Management by Objectives
b. Management by Exception
c. Management by Walking Around
d. Management by Control Limits

19. Which of the following is a characteristic of an effective reporting system?
a. SMART
b. KISS
c. MBO
d. LOWBALLING

20. Which of the following is an elapsed time task?
a. Paint is drying
b. A painter paints the wall
c. Software is being written
d. A sandwich is being made

21. An autocratic management style:

a. Is effective in most project management situations
b. Is effective in highly routine efforts
c. Is effective in high flux, state-of-the-art projects
d. Will lead to the tyranny of the majority

22. A project team structure that closely reflects the physical structure of the deliverable is known as:
a. Egoless
b. Specialty
c. Surgical
d. Isomorphic

23. The purpose of mid-project evaluation is:
a. Continual monitoring of budget and estimates
b. To focus on achievement of individual element of the project plan
c. To determine whether the original objectives are still relevant
d. To re-baseline the project budget

24. If the latest time you can start a task is five hours into the project, and the earliest time is three and a half hours into the project, how much slack (also called float) does the task have?
a. 0.5 hours
b. 1.5 hours
c. 2.5 hours
d. 8.5 hours

25. In risk management, insurance is an example of:
a. Risk avoidance
b. Risk deflection
c. Risk acceptance
d. Contingency planning

26. A four step risk assessment process reflecting standard risk management good practice consists of:
a. Risk identification, Risk deflection, Risk impact analysis, Risk monitoring and control
b. Risk acceptance, Risk impact analysis, Risk response planning, Risk monitoring and control
c. Risk deflection, Contingency planning, Risk impact analysis, Risk monitoring and control
d. Risk identification, Risk impact analysis, Risk response planning, Risk monitoring and control

27. Structured Walk-Through is a methodology used in:
a. PERT
b. GERT
c. VERT
d. Project Evaluation

28. If review of a project’s status indicates that EV = $400, AC = $400, and PV = $500, the project is:
a. On budget, behind schedule
b. On budget, ahead of schedule
c. Over budget, behind schedule
d. Over budget, ahead of schedule

29. The poor man’s hierarchy is a method for:
a. Project estimation
b. Project scheduling
c. WBS construction
d. Project selection

30. According to PMI, a WBS should focus on
a. Tasks
b. Deliverables
c. Interrelationships among activities
d. Cost of the project

31. If EV = $300, AC = $400, and the project budget is $1,000, what is the estimated final cost of the project (this is known as EAC, estimate at complete)?
a. $750
b. $1,000
c. $1,250
d. $1,333

32. Which of the following is a scope planning tool?
a. Benefit/cost analysis
b. WBS
c. Earned Value analysis
d. Fast tracking

33. In resource planning, one of the issues that needs to be considered is:
a. Staff empowerment
b. Technical requirements of the project
c. Theory X management principles
d. Theory Y management principles

34. The bottom-most level of the WBS — the level at which project budget and schedule data are captured — is called:

a. Work package
b. Code of accounts
c. Budget baseline
d. Change control level

35. Scope creep means:
a. Needs emergence and identification
b. Uncontrolled changes to a project’s requirements during project execution
c. Migration of project needs to requirements
d. Imprecise scope statement

36. Configuration management is a:
a. Methodology for working closely with customers by developing and updating requirements for faster response to changing customer needs
b. Methodology for ensuring that requirements evolve with evolving customer requirements
c. Methodology for specifying requirements at the outset and for controlling very tightly any changes to them
d. Methodology for specifying requirements at the outset and for facilitating any changes to them with minimum customer input

37. Rapid prototyping is a methodology for:
a. Specifying requirements at the outset and for controlling very tightly any changes to them
b. Specifying requirements at the outset and for facilitating later changes to them with minimum customr input
c. Triggering early warning of unauthorized changes to the original prototype to enable project management to take remedial actions
d. Working closely with customers by creating and updating prototypes that respond to customer input

38. Ensuring a one-to-one correspondence between specification items and general design items is a feature of:
a. Scope statement definition
b. WBS construction
c. Rapid prototyping
d. Configuration management

39. Under what conditions may a project manager accept a change request?
a. If the request has no effect on project objectives, deadlines, or resources.
b. If the request has no effect on project objectives, although it has effects on deadlines and resources
c. If the request is coming from a valued customer
d. If the request is from the Chief Executive Officer

40. Which of the following is not an activity carried out during project closeout?
a. Reassignment of project staff
b. Preparation of the project’s baseline
c. Reassignment of material resources
d. Preparation of user manuals

41. When crashing a project, we typically choose critical path tasks whose costs of crashing are highest.
True
False

42. The astute project manager typically uses only one management style in order not to confuse his/her teammates.
True
False

43. Concurrent engineering involves overlapping tasks and phases to accelerate a project’s schedule.
True
False

44. A work package is to be found at the summary level of the WBS.
True
False

45. Milestones, like tasks, consume resources.
True
False

46. In project management, the level of uncertainty plays a major role in determining the adequacy of a project plan.
True
False

47. Using working time or elapsed time to calculate the time it will take to complete a task produces the same results.
True
False

48. Needs recognition is the first stage of the needs-requirement life cycle.
True
False

49. Functional requirements provide us with detailed technical specifications.
True
False

50. A key objective of change control in configuration management is to keep track of actions taken in response to change requests.
True
False

51. Under rapid prototyping (also called application prototyping), the customer actually sees and works with the deliverable as it evolves.
True
False

52. There is a definite link between the level of risk an enterprise encounters and project time frame.
True
False

53. When we have objective data on the probability of an event, we are involved with decision making under certainty.
True
False

54. The Theory X approach to managing workers is a classic example of a top-down view of how people should be managed.
True
False

55. A laissez-faire management style may lead to a ship without rudder syndrome.
True
False

56. An objective of prototyping is to minimize life-cycle cost.
True
False

57. A modern view in Human Resource Management is that positive motivation results from an opportunity to achieve and experience self-actualization.
True
False

58. Confidence in the accuracy of a cost estimate increases when top-down and bottom-up estimates converge.
True
False

59. Internal Rate of Return (IRR) is the discount rate that sets the present value of cash outflow equal to the present value of cash inflow.
True
False

60. A project can be terminated prematurely because the original objectives may no longer be valid.
True
False

Homework Market
Calculate your paper price
Pages (550 words)
Approximate price: -

Why Homework Market

HomeworkMarket

Quality Researched Papers

We always make sure that writers follow all your instructions precisely. You can choose your academic level: high school, college/university or professional, and we will assign a writer who has a respective degree.

Homework Market

Qualified Writers

We have hired a team of professional writers experienced in academic and business writing. Most of them are native speakers and PhD holders able to take care of any assignment you need help with.

HomeworkMarket

Unlimited Revision

If you think we missed something, send your order for a free revision. You have 10 days to submit the order for review after you have received the final document. You can do this yourself after logging into your personal account.

HomeworkMarket

Timely Delivery

All papers are always delivered on time. In case we need more time to master your paper, we may contact you regarding the deadline extension. We will always strive to deliver on time.

HomeworkMarket

Original & Confidential

We use several writing tools checks to ensure that all documents you receive are free from plagiarism. Our editors carefully review all quotations in the text.

HomeworkMarket

Customer Support 24/7

Our support agents are available 24 hours a day 7 days a week and committed to providing you with the best customer experience. Get in touch whenever you need any assistance.

Try it now!

Calculate the price of your order

Total price:
$0.00

How it works?

Follow these simple steps to get your paper done

Homework Market

Place your order

Fill in the order form and provide all details of your assignment.

Homework Market

Proceed with the payment

Choose the payment system that suits you most.

Homework Market

Receive the final file

Once your paper is ready, we will email it to you.

Homework Market Writing Services

No need to work on essay at night. Sleep tight, we will cover your back. We offer all kinds of essay writing services.

HomeworkMarket HomeworkMrket

Essays

Essay Writing Services

No matter what kind of academic paper you need and how urgent you need it, you are welcome to choose your academic level and the type of your paper at an affordable price. We take care of all your paper needs and give a 24/7 customer care support system.

HomeworkMarket HomeworkMarket

Admissions

Admission Essays

An admission essay is an essay or other written statement by a candidate, often a potential student enrolling in a college, university, or graduate school. You can be rest assurred that through our service we will write the best admission essay for you.

HomeworkMarket HomeworkMarket

Editing

Essay Editing

Our academic writers and editors make the necessary changes to your paper so that it is polished. We also format your document by correctly quoting the sources and creating reference lists in the formats APA, Harvard, MLA, Chicago / Turabian.

HomeworkMarket HomeworkMarket

Research Paper

Research Paper

If you think your paper could be improved, you can request a review. In this case, your paper will be checked by the writer or assigned to an editor. You can use this option as many times as you see fit. This is free because we want you to be completely satisfied.